Storm Damage Repairs on E. Dunne Ave.

Update: As of 5/22/2018

Repair Locations:

        Site #2 – Near Finley Ridge Rd. Closure Location: Site #2 near Finley Ridge Rd.

Closure Location: Site #2 near Finley Ridge Rd.

Construction schedule:  Repairs are tentatively scheduled to start on May 29, 2018. Full road closure will be required. Road closure will be;
Monday through Thursday 8:00AM – 6:00 PM, with 15 minutes​ open window at 12:00  PM each day. 
Friday through Saturday 8:00 AM - 4:00 PM with 15 minutes open window at 12:00 PM each day.  

Construction Duration
: ​Approximately 6 weeks.